The Development Plan & Timeline

Proposed Plan for Park Redevelopment

We have secured enough funding to move to the Playground Preliminary Design Phase!

Application Phase

February 26, 2022

Thanks to everyone completing our Park Renewal Surveys, our Strategic Project Document was approved by the City of Edmonton. We provided the $5,000 deposit to…

Read more

The Concept Phase

March 1, 2022

Except in a tiny area, the concrete curbing is in good shape. We will be keeping the very popular spinning piece. It will be worked…

Read more

Playground Equipment Selection

June 20, 2023

Now that we have raised enough funds, we can move onto the Preliminary Design Phase.

Read more

Fundraising Phase 2

August 16, 2024

Total Project Cost, including for contingencies, has been budgeted at $775,000. From the 2015 to 2019 casinos of the League, we requested $25,000 be put…

Read more

Upcoming Fundraisers

No event found!

Park Fundraising – Total Goal $752,765

What have we Fundraised? (Updated Dec 11th, 2025)

Kensington Community League Fundraising Efforts

  • $100,227.5 |  Fundraising through AGLC
  • $53,381.70 | Local Fundraising Events
  • $25,000 | Area Council
  • $20,719.63 Corporate and Personal Donation
  • $13,045.16 KCL Events
  • $4,160.53 Interest on Saved Funds
  • $3,906.92 Miscellaneous
  • $2,513.70 | Bottle Drives
  • $2,125 | Newsletter Deliveries

Grants and Funds

  • $275,750 NPDP (Edmonton) Grant
  • $125,000 CFEP Grant (Alberta)
  • $20,000 Edmonton Community Foundation
  • $5,000 Allard Foundation

Fundraising in progress

  • $125,000 Accessibility Grant (Federal)
752765
650830.14

Stay Connected