The Development Plan & Timeline
We have secured enough funding to move to the Playground Preliminary Design Phase!

Application Phase
February 26, 2022
Thanks to everyone completing our Park Renewal Surveys, our Strategic Project Document was approved by the City of Edmonton. We provided the $5,000 deposit to…
Read moreThe Concept Phase
March 1, 2022
Except in a tiny area, the concrete curbing is in good shape. We will be keeping the very popular spinning piece. It will be worked…
Read morePlayground Equipment Selection
June 20, 2023
Now that we have raised enough funds, we can move onto the Preliminary Design Phase.
Read moreFundraising Phase 2
August 16, 2024
Total Project Cost, including for contingencies, has been budgeted at $775,000. From the 2015 to 2019 casinos of the League, we requested $25,000 be put…
Read more
Upcoming Fundraisers
No event found!
Park Fundraising – Total Goal $752,765
What have we Fundraised? (Updated Jan 24th, 2025)
Kensington Community League Fundraising Efforts
- $25,000 x 4 | Casino fundraising
- $25,000 | Area Council
- $63,890 | Local Fundraising Events
- $2,057 | Bottle Drives
- $2,125 | Newsletter Deliveries
- $840 | The Grocery People Community League Rebate Program
Donations
- $2,500 | April Glass and Mirror Ltd.
- $2,000 | Elsafadi’s
- $500 | Dollar Drug Mart
- $1,000 | Assiff Law Office
- $5,210 | Personal Donations
Grants and Funds
- $5,000 Allard Foundation
- $20,000 Edmonton Community Foundation
- $275,750 NPDP (Edmonton) Grant
Fundraising in progress
- $125,000 CFEP Grant (Alberta)
- $125,000 Accessibility Grant (Federal)